Why Eastland Port Chose GFRP Rebar for Its Biggest Infrastructure Upgrade in 100 Years
Eastland Port, located in Gisborne, New Zealand, is in the midst of its most significant infrastructure upgrade in a century. The Twin Berth project is designed to future-proof the port for generations, supporting the region’s forestry, horticulture, and agriculture export industries. With export tonnage exceeding three million tonnes per year, the port underpins a significant share of the regional economy.
We spoke with Mark Richards, Project Manager of the upgrade project at Eastland Group about why Mateenbar™ GFRP rebar was specified– and what it means for long-term asset performance.
Tell us about Eastland Port – its role in the regional economy, and the critical infrastructure challenges that come with operating a port in this coastal environment.
Mark Richards: Eastland Port is critical to the economic activity of the region, with forestry, agriculture and horticulture being key industries in the area. A major challenge is the ongoing preservation of concrete structures, where salt chloride ingress affects steel reinforcement. Managing that degradation is central to keeping the port operational and the infrastructure safe.
What specific corrosion-related challenges have you observed at Eastland Port over the years, and how have these impacted maintenance budgets and asset performance?
Mark Richards: Salt chloride ingress causes steel reinforcement to fail and spall – it compromises the concrete cover and, in the worst cases, wharf berths become unusable. That’s not just a maintenance cost issue, it’s an operational one. A berth out of service is lost productivity for the whole region. For a marine structure exposed to chloride ingress, removing reinforcement corrosion from the design equation was a significant advantage.
Engineers specified Mateenbar™ GFRP rebar for this upgrade project. What drove the decision to move away from traditional steel reinforcement – and why Mateenbar™?
Mark Richards: There were two main drivers. The corrosion resistance of Mateenbar™, which will outlive the projected life of the asset. And the significant savings on the hiring and use of heavy plant – Mateenbar™ is a quarter of the weight of steel rebar, which reduced payload and associated costs considerably.
Why choose Mateenbar™ over another GFRP supplier? What were the key considerations?
Mark Richards:
Several things. We’d used Mateenbar™ on previous projects and it had performed well, so there was already confidence in the product. Lead times and turnaround on design changes were fast, which helped keep the project on schedule. Previous Eastland Group project managers had also passed on positive experiences with Mateenbar™. Having a local supplier with technical support available throughout the design and construction phases was another benefit.
From an asset management perspective, how did you evaluate whole-of-life costs of GFRP versus conventional steel rebar?
Mark Richards:
Eastland Port had already used Mateenbar™ successfully on previous projects, so there was confidence in the material. From an asset management perspective, reducing the long-term risk of corrosion-related repairs and maintaining asset availability were important considerations when assessing the solution.
How does the 100-year design life of GFRP rebar align with Eastland Port’s long-term asset strategy?
Mark Richards: The design life of the structure was a key consideration, and Mateenbar™ exceeded it. In a marine environment, eliminating reinforcement corrosion as a deterioration mechanism gives greater confidence in the long-term performance of the asset. When your reinforcement outlasts the concrete it’s embedded in, you’ve removed a significant variable from your long-term asset management plan.
What advice would you give to other port or infrastructure asset owners considering GFRP solutions?
Mark Richards: It will definitely be considered for future projects. The local supplier relationship means technical support is available when you need it. And the results speak for themselves – the wharf deck was operational within a week of final engineering sign-off, and production hasn’t stopped since. Kiwifruit and log exports kept moving.